ZENORA - OFFICE BUILDING

Construction of a real-estate complex in Issy-les-Moulineaux. HQE building, BBC Effinergie building, BREEAM building, ISSEO+ level quality charter with the city of Issy-les-Moulineaux.
ZENORA - Immeuble à usage de bureaux

ZENORA - OFFICE BUILDING

FAYAT BÂTIMENT Île-de-France is in charge of the construction of an office building: the project is divided into separate packages. The construction work includes the carcassing package and structural steel work split into 2 parts: infrastructure of 3 basement levels with 620 parking spaces for cars and 400 spaces for 2 motorbikes as well as machinery rooms; A “VEGA” office building (NFA: 24,529²), also including “laboratories” and a staff canteen. The second part concerns a “NODA” office building and a catering centre.

28 months

OF CONSTRUCTION

€75,000,000

excl. V.A.T.

2,464 t

OF STEEL

28,000 m³

CONCRETE