The work is being carried out in four distinct phases.
Phase 1 :
- Preparatory work (construction of the future South parking platform and site facilities)
- Construction work: installation of a fluid connection to the cafeteria, completion of the cafeteria's watertight and airtight structure, connection to the main electrical panel, and completion of the housing units (all trades)
Phase 2 :
- Watertight and airtight structure of buildings C and E and structural extension
Phase 3 :
- Watertight and airtight structure of buildings A and B
Phase 4 :
- Watertight and airtight structure of building D
- Reconstruction of the facades of building H
The school remained open throughout the duration of the work.