An extension integrated into a fully operational hospital site
The project involves the construction of a three-storey building over a partial basement, comprising two floors dedicated to medical and surgical units and one floor for paediatrics and neonatology.
The new facility will accommodate four medical and surgical units providing a total of 98 beds, together with a 19-bed paediatric floor incorporating outpatient consultation areas, a day hospital, patient rooms and an intensive care unit. The building has been designed around a 600 m² landscaped central garden, while the basement provides a logistical connection with the existing building. At garden level, a direct link connects the surgical departments to the existing operating theatres.

One of the main challenges of the project lies in carrying out the works in close proximity to fully operational facilities, while maintaining maternity, dialysis and operating theatre activities. The project also includes a connecting footbridge to the existing building, requiring the adaptation and creation of openings, as well as works within the hospital to connect certain primary utility networks.
The structure of the new building is based on a column-and-beam system with concrete façades, requiring approximately 3,500 m³ of concrete and 180 tonnes of steel.
Bioclimatic design supporting environmental performance
The project is based on the three key principles of bioclimatic architecture: reduced energy demand, efficiency and the use of renewable energy sources.
The design aims to achieve performance levels exceeding regulatory requirements, with targets covering Bbio, energy consumption, carbon emissions and occupant comfort. The project also incorporates the use of low-carbon concrete and is targeting BDNA Silver-level certification.
The objectives include energy consumption below regulatory thresholds and a carbon performance target aligned with the RE2025 threshold under RE2020. User comfort is also a key consideration, with specific targets for hygrothermal comfort and daylight autonomy.