A carefully phased project on an operational site
The project includes the refurbishment of the existing park-and-ride facility, which currently provides 603 spaces, together with the construction of an extension creating approximately 280 additional parking spaces. The works also cover roadways and external areas in order to adapt vehicle circulation and pedestrian routes, while allowing for a future pedestrian connection to the Pont des Collines.
The works are being carried out while the site remains operational, with continued access for motorists, buses, trams and cyclists. This constraint requires a carefully planned sequence of construction phases and temporary traffic diversions. Site preparation notably includes the redevelopment of public spaces, the VCub cycle hire facilities, the bus stop and the roundabout, as well as the creation of a new drop-off area and a temporary bus lane.

The structural works include the construction of the foundations, with secant pile retaining walls, piles and micropiles. They also include cast-in-place white architectural concrete walls with a textured finish. The car park extension is being built first, followed by the refurbishment and structural strengthening of the existing facility, organised in two phases to ensure that it remains operational throughout the works.
An environmental approach integrated into the project
The project incorporates several environmental measures. The refurbishment of the existing park-and-ride facility notably includes the creation of a green roof incorporating photovoltaic panels.
The project also forms part of a high environmental quality approach and includes the use of low-carbon concrete for the works.