A major construction project
Located on a 16,500 m² site in Montpellier’s Euro Médecine district, the project includes the demolition of the existing buildings followed by the construction of two new facilities:
- a three-storey training building (4,082 m² of floor area), incorporating a shooting range, two dojos, a road training area, simulation spaces, several training rooms and administrative offices;
- a catering building (812 m² of floor area), comprising a 300-seat restaurant and the associated technical areas.
The works involve special foundations adapted to the site constraints, followed by a reinforced concrete structural frame. This eight-month phase requires the installation of two tower cranes to secure material handling and optimise the pace of construction.
The structure of the training building consists of a concrete base with a column-and-beam frame, complemented by timber-framed façades. For the catering building, the process area is constructed in concrete, while the restaurant section features timber façade infill. The project also includes external cladding, waterproofing works and a steel roof structure.
A construction approach designed to reduce the project’s carbon footprint
The project combines concrete and timber to balance structural robustness, thermal mass and energy performance. The extensive use of timber framing across the façades significantly reduces the carbon emissions associated with construction, while also enhancing the building’s thermal insulation.
This mixed construction approach helps limit the project’s environmental impact while improving indoor comfort for users.