A project carried out on an occupied school site
The project involves the extension and refurbishment of a school complex comprising two nursery schools and one primary school, totalling 23 classrooms, as well as a dining hall and a sports hall.
The works include bringing the two nursery schools together in a new nine-classroom building, the refurbishment and extension of the 14-classroom primary school, the reconfiguration of the dining hall and the construction of the sports hall. All works are being carried out on an occupied site in order to maintain continuity of teaching activities and ensure the continued use of the existing facilities.
The project is being delivered in three main phases: 6 months of design, 30 months of construction works and 60 months of operation and maintenance.
An exemplary project in terms of energy and environmental performance
The project incorporates solutions designed to optimise energy performance and reduce its environmental impact.
The thermal refurbishment of the existing buildings, energy-efficient extensions and the installation of sustainable equipment all contribute to efficient and environmentally responsible operation.
Reducing disruption and maintaining school activities throughout the works also demonstrate the attention paid to user comfort, quality of life and the long-term sustainability of the project.