Restructuring a school complex on an occupied site
The project involves transforming an existing school site into a complex comprising 28 classrooms, including 10 nursery school classrooms and 18 primary school classrooms.
The development is organised around three main three-storey buildings (ground floor plus two upper floors), complemented by ancillary buildings dedicated to extracurricular activities, a community association facility, caretaker accommodation, a sports hall and a boxing club. A catering facility completes the complex.
The works are being carried out while the schools remain operational throughout the construction period. This constraint requires a carefully phased swing-space approach, ensuring safe circulation routes, strict separation between construction areas and occupied spaces, and uninterrupted access to educational facilities for pupils.
Synergies within the Fayat Group
The entire project is being delivered by a consortium comprising Bec Construction Provence, FBEI, FB3M and Semeru. Their complementary expertise ensures overall consistency throughout the design-and-build process, the integration of technical building systems and effective management of performance requirements.
Environmental performance integrated into the project
The project incorporates measures aimed at reducing its carbon footprint through the selection of appropriate materials and construction methods. The use of low-carbon concrete, for example, helps reduce emissions associated with the main building structures. The refurbishment of the existing buildings also contributes to improving the overall energy performance of the site, with the aim of reducing energy consumption.